Maldives Transport and Contracting Company (MTCC) has achieved 46% overall completion on the "Design and Build of AA. Feridhoo Harbour Upgrade" project, with pavement compaction and concrete operations currently underway on-site.
The MVR 50.8 million development project—awarded on January 16, 2023, and mobilized on August 15, 2023—features a wide infrastructural scope designed to overhaul the island’s maritime access.
Key deliverables and structural components under the project scope include:
Shore Protection: 550 meters of rock boulder installation
Quay Wall: 213 meters of precast L-block quay wall construction
Dredging Operations: 35,695 cubic meters of basin and channel dredging
Harbour Paving: 2,481 square meters of pavement installation
Jetty Construction: 80-meter jetty structure
Bridge Construction: 12-meter connecting bridge
According to MTCC, the completed infrastructure will resolve congestion, provide resilient breakwater and revetment defenses, and ensure secure docking for vessels operating in AA. Feridhoo.